Starting the renovation works of Risti 110 kV substation

Starting the renovation works of Risti 110 kV substation

AS Connecto Eesti and Elering AS signed the contract for the renovation of the Risti 110 kV substation. The cost of construction works is 1.49 million euros and the final delivery of works to the client is due to take place in June 2020.

The substation located in Läänemaa will be built based on the turn-key contract. The required equipment will be designed and delivered in the course of the renovation works. The existing 110 kV switchyard will be demolished. The new management building, ducts, oil collection and separation system for the 110 kV transformers and stormwater drainage system of the territory will be built. The delivered equipment will be installed, adjusted and supplied with new management, aid and control systems. The reconnecting of existing lines to the new switchyard and the powering of the substation will be carried out in April 2020. The project manager of Connecto is Aleksander Mamai.