Replacement of gas pipe sections on Haljala-Loobu T135

Replacement of gas pipe sections on Haljala-Loobu T135

The gas pipe section replacement works in Haljala-Loobu have begun. In the scope of the contract with Elering AS, the gas transfer pipeline at Kadrina-Viitna road and Loobu river crossings will be replaced. The crossing with Loobu river will be constructed with targeted drilling, during which a hollow for the gas pipeline with 1 m diameter and 170 m length will be placed under the river. During the construction, almost 600 m of high-pressured gas pipe will be replaced, tests will be run and new measuring points will be installed. The cost of the contract is 780 000 Euros and the final deadline of works is October 2020. The project manager from Connecto is Raul Osman.